More than one nexttask in gantt graph

TeeChart for ActiveX, COM and ASP
Post Reply
Morpheu
Newbie
Newbie
Posts: 2
Joined: Fri Nov 15, 2002 12:00 am
Location: Brazil
Contact:

More than one nexttask in gantt graph

Post by Morpheu » Tue Mar 09, 2004 2:39 pm

Hello all,

I need put more than one nexttask in gantt graph to use him how a Project.

It is possible?

Thanks for help,

Morpheu

Pep
Site Admin
Site Admin
Posts: 3278
Joined: Fri Nov 14, 2003 5:00 am
Contact:

Post by Pep » Wed Mar 10, 2004 9:49 am

Hi Morpheu,

each Gantt bar can be connected only to one "next task". If you need more than one connection per Gantt bar, then the only way to do it is to add more GanttSeries, populate it with the same Start, End and Y values and then use each series for different connection (different NextTask for each series).

Morpheu
Newbie
Newbie
Posts: 2
Joined: Fri Nov 15, 2002 12:00 am
Location: Brazil
Contact:

Post by Morpheu » Thu Mar 11, 2004 1:57 pm

Hi,

Thanks for help, but I can make one question?
Exists plan for improve this feature?
To create more series is not the best solution, mainly when I have to reproduce a project accompaniment that have for each task: planned, accomplished, new forecast.
Pep wrote:Hi Morpheu,

each Gantt bar can be connected only to one "next task". If you need more than one connection per Gantt bar, then the only way to do it is to add more GanttSeries, populate it with the same Start, End and Y values and then use each series for different connection (different NextTask for each series).
Thanks for help,

Morpheu

Pep
Site Admin
Site Admin
Posts: 3278
Joined: Fri Nov 14, 2003 5:00 am
Contact:

Post by Pep » Tue Mar 16, 2004 8:49 am

Hi Morpheu,

I've add this feature on our wish list to be considered to inclusion for the next releases of TeeChart.

Post Reply